Diggers on Display

January 2013

Working with Davlyn Construction, Respol have completed a 530m2 project for JCB at their Uttoxeter Design Centre. The flooring for the new display area was completed during a two-week period.

The change of use for the area required a total upgrade to give a finish suitable for display of products.

We shot-blasted the complete area to remove all old residues and flooring paints, prepared the cleaned substrate with a DPM primer and then installed our own Reetop P2000. This was then followed up with the installation of our Reeflor EL1001 product.